GameChange Solar is expediting racking production to beat year-end rush
October 14, 2016
GameChange Solar sent word that production for piles in two through three weeks and three through four weeks for racking through year end. The service is for pile driven racking systems for orders up to 30 MW. For larger orders, up to 150 MW, production starts at two weeks for piles and three weeks for racking and completes one to three weeks later respectively.
Derick Botha, VP of Business Development for GameChange Solar, stated: “Many customers have rush requirements for year end and we are standing by with multiple dedicated lines ready to service their important needs.”
For more on GameChange Solar, hit their website.